The DEIS for the I-270/US 15 Multi-Modal Corridor Study, supplemented by other segment data provided, contains engineering and background information that can be used to determine respondent interest in the overall I-270 multi-modal corridor as a P3 project.
The Offeror shall submit a narrative responding separately to each of the questions listed below in this Section. The narrative response to all questions in this section is expected to comprise about fifteen (15) pages.
i) Questions
A) Response Format
Submissions shall be prepared simply and economically and shall provide a clear description of the Offeror’s Response to the information request. Oral or facsimile submissions will not be accepted. The Offeror’s Response may be submitted in electronic format (by email or CD), but at least one (1) paper copy, which must be unbound and ready for easy reproduction, should follow within two working days of submittal of the electronic version.
The Response submitted shall include:
Offeror’s Response may include other material indicative of Offeror’s interest in partnering with the State for I-270 Corridor development, but the overall response shall not total more than twenty-five (25) pages, inclusive of response to the Section III Questions.
B) Administrative Information
C) Minority Business Enterprise Participation
The State of Maryland encourages Minority Business Enterprises (MBE) to participate in all contracts. The sponsoring Maryland transportation agencies hereby notify all Offerors that in regard to any contract entered into subsequent to this RFEI, MBEs will not be subject to discrimination on the basis of race, color, sex or national origin in consideration for an award. MBEs are encouraged to respond directly to this RFEI.
D) Glossary of Abbreviations
| BRT | Bus Rapid Transit |
| CCT | Corridor Cities Transitway |
| DEIS | Draft Environmental Impact Statement |
| EA | Environmental Assessment |
| ETL | Express Toll Lanes |
| FEIS | Final Environmental Impact Statement |
| GPL | General Purpose Lanes |
| HOV | High-Occupancy Vehicle |
| LRT | Light Rail Transit |
| MBE | Minority Business Enterprise |
| MDOT | Maryland Department of Transportation |
| The Authority | Maryland Transportation Authority |
| MTA | Maryland Transit Administration |
| NEPA | National Environmental Policy Act |
| PPP or P3 | Public-Private Partnership |
| RFEI | Request for Expression of Interest |
| SHA | State Highway Administration |
| TBD | To Be Determined |
E) Anticipated Schedule of Activities
| Activity | Date |
| RFEI Published | October 11, 2006 |
| Pre-submission Conference | November 21, 2006 |
| Cut-off for Questions | December 5, 2006 |
| Deadline for Submittals | December 19, 2006 |
| Review Team Meets | TBD |
| Oral Presentations | As needed |
| Team Makes Recommendations | TBD |
| RFP-Step 1 Issued | TBD |
| Project Study Schedules | |
| I-270/US 15 Multi-Modal Study: Environmental Assessment |
May 2007 |
| Agency Completion of FEIS | August 2008 |
| I-495 West Side Mobility Study: Develop Preliminary Concepts |
Winter 2006/07 |
| Receive Logical Termini | Spring/Summer 2007 |
I-270 from I-370 to I-495 (ETL) Complete Feasibility Study |
Fall 2006 |
| NEPA Study | TBD |